To begin with , we should give "TICKET" to you for not knowing it.
End user is not able to
1. Create Sales order for a customer from a New plant , since shipping point determination is not happened . ( Without Shipping point the document becomes INCOMPLETE and he will not be able to proceed further like DELIVERY, BILLING).
He raises a ticket and the priority is set in one of the below:
1. Low
2. Medium
3. High.
Now you need to solve this ticket. You would analyze the problem and identify that the SP configuration has to be done for the new plant.
You would request a transport for DEV CLIENT to BASIS. You do the change and Request one more Transport to BASIS for QA client. The End user will test the same by creating a sales order for the new plant and approve it.
Finally, you request a transport to move the changes to PRODUCTION. Once the change is deployed in production the TICKET is closed. What I have given is a small example. You would get some real issues with severity HIGH in your day-day support.